Two years, sequenced so each stage earns the next
The RFP asks for a roadmap that recognizes municipal budget cycles, procurement lead times, public records obligations, varying departmental readiness and limited staff capacity. That rules out a plan where everything starts at once.
The shape below is governance first, then the inventory, then one proved use case, then extension, then internal retrieval, then the first agent. Each stage ends at a decision gate the City passes or does not. A stage that fails its measure does not advance, and that is a success of the method, not a failure of the project.
Quarter 1: Decide how agents are governed
- Write the agent lifecycle Policy 2.2 does not cover: who requests, who approves data and permissions, how it is tested, who supports it, how it is monitored, how it is retired.
- Answer the records question in section 8.4: how the City retrieves Copilot prompts and outputs when the Clerk asks.
- Replace the 30 percent attribution rule with one the City can actually apply.
- Stand up the AI request queue so every idea has one route and a visible decision.
Decision gate: Governance that exists on paper and in a queue. Investment: $0 in new software.
Quarter 1 and 2: Finish the inventory the public scan started
- Confirm the 18 systems visible from outside and add the internal estate: finance, public safety, permitting, records, HR.
- For each one record business and technical owner, hosting, sensitivity, retention, integration and vendor constraints.
- Mark where the same fact is held in more than one place, which is where reporting and AI both go wrong.
- Review the SharePoint permission model, because that is what decides what Copilot can see.
Decision gate: An inventory the City maintains, not a consultant's PDF. Investment: Staff time, plus optional tooling.
Quarter 2: Prove the pattern on published content
- Build resident question answering grounded only in published pages and the Code of Ordinances.
- Measure deflection, accuracy and the hours it returns to staff.
- Publish the measure. If it does not meet it, retire it.
Decision gate: One working use case with a number attached. Investment: Low; existing licenses.
Quarter 3 and 4: Extend to the service request corpus
- Summarization and routing on SeeClickFix, with names removed before processing.
- A person confirms routing until the measure justifies otherwise.
- Train the departments that receive the routed work, not only the ones that send it.
Decision gate: Faster routing, measured. Investment: Low to moderate.
Year 2, first half: Internal retrieval, once permissions are fit
- Remediate SharePoint permissions on the sites in scope.
- Grounded retrieval for staff across the remediated estate.
- Role-based training, because retrieval fails on how people ask, not on the model.
Decision gate: Staff can find what they are entitled to find. Investment: Moderate; premium licensing decision.
Year 2, second half: First agent through the full lifecycle
- Pick one agent with a narrow write scope and run it through the governance built in quarter 1.
- Decision gate before it writes to any system of record.
- Review every agent in service; retire the ones that stopped earning their place.
Decision gate: An agent in production the City can switch off. Investment: Moderate.
What this is not
It is not a product selection. The RFP asks for IT capabilities and tool categories without limiting recommendations to a particular vendor, and ECI holds no reseller or referral arrangement with any AI vendor. Where a capability is needed, the roadmap names the capability. Where the City already owns something that provides it, as it does with Copilot and with ArcGIS, the roadmap says to use what the City owns before buying anything.
Where the money goes
Most of the first year is staff time and decisions, not software. The City already holds the licences for the first three use cases. The two places real money appears are premium licensing, once internal retrieval is justified by a measure, and the permission remediation that has to happen before retrieval is safe. Both are decisions the City makes with evidence from the stage before, which is why they sit in year two and not in the proposal.